Air
conditioning has become very important nowadays, because global warming and
other environmental conditions have made uncomfortable atmosphere around us. So
air conditioning system will be the very important part of a building in
future.
As
a mechanical engineers, we must know the process of designing air conditioning
system. That design process has been linked with thermodynamics and also fluid
dynamics. So engineers should have sound knowledge around those two field.
Cooling
load estimation is the first step to controlled air-conditioning. Air-conditioning
is utilized to supply a controlled atmosphere to public buildings such as
offices, halls, homes, and industries for the comfort of human being or for the
proper performance of some industrial processes. When considering cooling load,
it becomes very important to consider the way that building heat gain occur. It
can be clearly illustrated as following.
Figure No 01 : Building Total Heat Gain
Factors
Full
air-conditioning implies that the purity, movement, temperature and relative
humidity of the air be controlled within the limits imposed by the design
specification. For any air conditioning system to perform satisfactorily,
equipment of the proper capacity must be selected based on the instantaneous
peak load requirements. The type of control used is dictated by the conditions
to be maintained during peak and partial load. Undersized equipment will not
provide the required conditions while a greatly oversized one will lead to
operating problems such as “hunting”. Load estimating in air-conditioning
system design has been carried out manually in many quarters in developing
country .A lot of time and energy are wasted when estimating the cooling loads
in complex and intricate buildings of modern time. But here manual calculation
process is described
There
are two steps to be done to install good air conditioning system, they are
- Estimating cooling load of the building
- Duct designing process
Estimating cooling load of the
building
Cooling
load estimation is a very important and complex task when it is done manually.
There are three methods to estimate cooling load for a particular building,
they are
- Transfer Function Method (TFM) : This is the most complex of the methods proposed by ASHRAE and requires the use of a computer program or advanced spreadsheet.
- Cooling Load Temperature Differential/Cooling Load Factors (CLTD/CLF) : This method is derived from the TFM method and uses tabulated data to simplify the calculation process. The method can be fairly easily transferred into simple spreadsheet programs but has some limitations due to the use of tabulated data.
- Total Equivalent Temperature Differential/Time-Averaging (TETD/TA) : This was the preferred method for hand or simple spreadsheet calculation before the introduction of the CLTD/CLF method.
For
strictly manual cooling load calculation method, the most practical to use is
the CLTD/CLF method as described in the 1997 ASHRAE Fundamentals. This method,
although not optimum, will yield the most conservative results based on peak
load values to be used in sizing equipment. It should be noted that the results
obtained from using the CLTD/CLF method depend largely on the characteristics
of the space being considered and how they vary from the model used to generate
the CLTD/CLF data shown on the various tables.
Considerations
and Assumptions
- Design cooling load takes is done by making lot of assumptions some of them can be mentioned as following.
- Weather conditions are selected from a long-term statistical database. The conditions will not necessary represent any actual year, but are representative of the location of the building. ASHRAE has tabulated such data.
- The solar loads on the building are assumed to be those that would occur on a clear day in the month chosen for the calculations.
- All building equipment and appliances are considered to be operating at a reasonably representative capacity.
- Latent as well as sensible loads are considered.
- The latent heat gain is assumed to become cooling load instantly, whereas the sensible heat gain is partially delayed depending on the characteristics of the conditioned space. According to the ASHRAE regulations, the sensible heat gain from people is assumed 30% convection (instant cooling load) and 70% radiative (delayed portion).
- The ventilation rates are either assumed on air changes or based on maximum occupancy expected.
- Design dry blub of 2.5% in summer and 97.5% in winter for Chittagong city is considered. 2.5% means that temperature exceeds the value (330C) only 2.5% of all the hours in summer months. Windows are externally shaded.
As
above mentioned manner Cooling Load Temperature Differential/Cooling Load
Factors (CLTD/CLF) is the most accurate and most widely used method. Following
this method it is very easy to find cooling load for any space of a particular
building. After estimating cooling load, next step is duct designing.
Air
flow rates should be calculated for each and every space of the building. It is
done by using estimated cooling load
values. To do that psychrometric chart
can be used.
In here both sensible and latent heat transfer
take place. For sensible heat transfer, the driving potential is the
temperature differential. For the latent heat transfer the driving potential is
partial pressure difference or the corresponding specific humidity difference.
By considering energy balance for latent or sensible heat transfer we can find
mass flow rate for particular building space (room). By following same method
all the required mass flow rates can be calculated. After that air flow rates
can be calculated
Duct designing process
Duct
designing is the most critical task in air conditioning system designing.
Engineers have responsibility to design very effective duct system by
considering several factors. The chief requirements of an air conditioning duct
system can be mentioned as following manner.
- It should convey specified rates of air flow to prescribed locations
- It should be economical in combined initial cost, fan operating cost and cost of building space
- It should not transmit or generate objectionable noise
Although
engineers have achieved major requirements of duct designing, those things will
not be enough. Because to install very effective duct system, design engineers
must consider following general rules for duct design
- Air should be conveyed as directly as possible to save space, power and material
- Sudden changes in directions should be avoided. When not possible to avoid sudden changes, turning vanes should be used to reduce pressure loss
- Diverging sections should be gradual. Angle of divergence ≤ 20o
- Aspect ratio should be as close to 1.0 as possible. Normally, it should not exceed 4
- Air velocities should be within permissible limits to reduce noise and vibration
- Duct material should be as smooth as possible to reduce frictional losses
Duct
systems can be classified as following manner. According to that classification,
we have to select suitable air flowing velocity for the system.
- Low pressure systems : Velocity ≤ 10 m/s, static pressure ≤ 5 cm H2O (g)
- Medium pressure systems: Velocity ≤ 10 m/s, static pressure ≤ 15 cmH2 O (g)
- High pressure systems: Velocity > 10 m/s, static pressure 15<p ≤ 25 cm H2O (g)
When
considering air velocity, engineers have to consider lot of factors. Because
they have to select optimum velocity for the system otherwise lot of problems
can occur. There are air velocity standard table for that, so referring those
tables air velocity can be calculated. Recommended air velocities depend mainly
on the application and the noise criteria. Typical recommended velocities are
- Residences: 3 m/s to 5 m/s
- Theatres: 4 to 6.5 m/s
- Restaurants: 7.5 m/s to 10 m/s
When
we have high velocities in the ducts results in
- Smaller ducts and hence, lower initial cost and lower space requirement
- Higher pressure drop and hence larger fan power consumption
- Increased noise and hence a need for noise attenuation
Duct
system design become very difficult when we have huge buildings. So engineers
should identify the lot of parameters for that. Generally at the time of
designing an air conditioning duct system, the required airflow rates are known
from load calculations. The location of fans and air outlets are fixed
initially. The duct layout is then made taking into account the space available
and ease of construction. In principle, required amount of air can be conveyed
through the air conditioning ducts by a number of combinations. However, for a
given system, only one set results in the optimum design. Hence, it is
essential to identify the relevant design parameters and then optimize the
design.
The
run with the highest pressure drop is called as the index run. From load and
psychrometric calculations the required supply airflow rates to each
conditioned space are known. From the building layout and the location of the
supply fan, the length of each duct run is known. The purpose of the duct
design is to select suitable
dimensions
of duct for each run and then to select a fan, which can provide the required
supply airflow rate to each conditioned zone.
Due
to the several issues involved, the design of an air conditioning duct system
in large buildings could be a sophisticated operation requiring the use of
Computer Aided Design (CAD) software. However, the following methods are most
commonly used to design duct systems
- Velocity method
- Equal Friction Method
- Static Regain method
Very
effective and easy method to design duct systems is equal friction method,
because other to methods can be a result to have large pressure drops. So brief
introduction about equal friction method as follows.
In
this method the frictional pressure drop per unit length in the main and branch
ducts (Δpf/L) are kept same. After that we can follow the procedure, because we
have already calculated air flow rates and air velocity for the application.
- Select a suitable frictional pressure drop per unit length (Δpf/L) so that the combined initial and running costs are minimized.
- Then the equivalent diameter of the main duct is obtained from the selected value of (Δpf/L) and the airflow rate airflow rate in the main duct.
- Since the frictional pressure drop per unit length is same for all the duct runs, the equivalent diameters of the other duct runs, can be found by considering frictional pressure drop equation.
- If the ducts are rectangular, then the two sides of the rectangular duct of each run are obtained from the equivalent diameter of that run and by fixing aspect ratio as explained earlier. Thus the dimensions of the all the duct runs can be obtained. The velocity of air through each duct is obtained from the volumetric flow rate and the cross-sectional area.
- Next from the dimensions of the ducts in each run, the total frictional pressure drop of that run is obtained by multiplying the frictional pressure drop per unit length and the length.
- Dynamic pressure losses in each duct run are obtained based on the type of bends or fittings used in that run.
- The total pressure drop in each duct run is obtained by summing up the frictional and dynamic losses of that run.
- The fan is selected to suit the index run with the highest pressure loss. Dampers are installed in all the duct runs to balance the total pressure loss.
After
following above mentioned steps, duct system design process will be finished.
Then engineers should implement installations process according to the design
data.
Figure
No 02 : Air Conditioning Systems Layout and Types
References
- ASHRAE, (1997). ASHRAE Fundamentals Handbook, American Society of Heating, Air-Conditioning and Refrigeration Publishing Service.
- ASHRAE, (1989). ASHRAE Fundamentals Handbook, American Society of Heating, Air-Conditioning and Refrigeration Publishing Service.
- C.P Arora, Refrigeration and Air Conditioning, Second Edition.
If summertime temperatures leave you hot under the collar, you’re not alone. A top dissertation writing services researched that that today’s air conditioners are more energy efficient which means they cost less to run while keeping you calm, cool as well comfy.
ReplyDelete